AMD Xilinx 7 Series Lead Times Hold at 52 Weeks: November 24 Snapshot

In today’s measured check (November 24, 2026), every core AMD Xilinx 7-series and Zynq-7000 part we track shows the same factory lead time at Mouser: 52 weeks. Eight of the ten core parts show zero stock. The only exceptions are the Artix-7 XC7A35T-2FTG256I, with 430 pieces available, and the Spartan-6 XC6SLX16-2FTG256I, with 99 pieces and a shorter 23-week lead time.

One honest note on today’s reading: DigiKey blocked our checks for a third straight day, so the figures below are Mouser’s live readings (November 24, 10:14–10:53 CST). Where a second channel could not be re-checked, we say so — we do not present an older reading as today’s.

The snapshot (Mouser, November 24, 2026):

  • XC7K410T-2FFG900I — 0 in stock; 52 weeks; next 4 pieces expected February 8, 2027
  • XC7K160T-2FFG676I — 0 in stock (listed as non-stocked); 52 weeks
  • XC7K325T-2FFG900I — 0 in stock (listed as non-stocked); 52 weeks
  • XC7Z045-2FFG900I — 0 in stock; 52 weeks; next 4 pieces expected January 11, 2027
  • XC7Z020-2CLG484I — 0 in stock; 52 weeks; next 255 pieces expected July 29, 2027
  • XC7Z030-2FFG676I — 0 in stock; 52 weeks; next 191 pieces expected August 27, 2027
  • XC7A100T-2FGG484I — 0 in stock; 52 weeks; next 146 pieces expected June 11, 2027
  • XC7A35T-2FTG256I — 430 pieces in stock; 52 weeks
  • XC6SLX16-2FTG256I — 99 pieces in stock; 23 weeks
  • XCKU060-2FFVA1156I — 0 in stock (listed as non-stocked); 40 weeks

What this means for buyers

  • 52 weeks is the planning horizon, not a blip. Nothing in the core range moved this week — every part held exactly where it was on November 23. If your build date falls inside the next 12 months, a factory lead-time quote will not reach you in time. Confirm a lot from existing stock instead of waiting on a lead time.
  • The next factory lots are small and far away. The earliest arrivals are just 4 pieces each of the Kintex-7 XC7K410T (February 8, 2027) and the Zynq-7000 XC7Z045 (January 11, 2027). Larger lots — 255 pieces of the XC7Z020, 191 of the XC7Z030 — do not arrive until mid-to-late 2027. A 4-piece lot covers a prototype, not a production run.
  • Two lines still have stock today — and they are the exception. The Artix-7 XC7A35T holds 430 pieces and the Spartan-6 XC6SLX16 holds 99 pieces, both unchanged for three days. The SLX16 also carries the shortest lead time in the core range at 23 weeks. If either part is on your BOM, that is the line to confirm first.
  • The second channel could not be checked today. DigiKey blocked our checks for a third day in a row, so the DigiKey readings quoted in earlier articles are the last verified ones, not today’s. We will re-check as soon as access returns. A zero at one channel has before turned out to be stock at another — the A35T read zero at DigiKey on November 21 and still held 430 pieces at Mouser and 74 at Newark on November 23.
  • One RF watch item. Mini-Circuits PMA-183PLN+ had 1,865 pieces due at Mouser today (November 24) and had not arrived at our morning check. We will confirm tomorrow whether the lot landed.
  • Price-rise watch, one line. The reported AMD increase for December 27 remains unconfirmed by the factory. ST’s fourth increase takes effect January 1, 2027.

If any 7-series or Zynq line on your BOM needs a confirmed lot, send us your shortage list. We check real availability lot by lot. Request a Quote

We reply to every inquiry within 24 hours.