Analog IC shortages are not easing — they are running into 2027. DigiTimes reported on November 27 that analog IC shortages persist despite AI uncertainty, with supply the key concern for 2027. TrendForce’s November 24 report gives the detail: demand from AI and industrial applications is rebounding, while shrinking 8-inch wafer capacity tightens supply further.
What the reports say:
- STMicroelectronics is preparing another price increase on selected products from January 1, 2027 — its fourth adjustment in 2026, following three price adjustment notices already issued this year (TrendForce, citing Commercial Times). The size of the increase and the product list have not been published.
- Around 80% of NXP’s products now carry lead times over 16 weeks, up from about 25% a year earlier. NXP’s book-to-bill ratio remains well above one across all end markets, and its order backlog extends further into 2027 (NXP earnings call, via Benzinga).
- Microchip expects foundry and packaging prices to rise again in January 2027. CEO Steve Sanghi said major foundries and packaging and testing providers will raise prices again in January; Microchip raised its own prices in August and plans to absorb the additional costs for now (earnings call transcript, via GuruFocus).
- TI prices are already up 10–15%, according to a Deutsche Bank distributor survey cited in Macrostream’s November shortage tracker. TI’s third-quarter revenue was US$6.06 billion, up 28% year on year, with growth in industrial, automotive and data centre markets.
- ADI’s price index is also rising, to 102.36 in the same survey, while ST’s remains at a low 84.40.
- 8-inch wafer capacity is shrinking, and AI data centre and robotics demand is absorbing available capacity, while investment in the mature technologies used for diodes, transistors and other basic components has lagged for years (Reuters, via Nexperia and STMicroelectronics chief executives).
Our measured check today (November 27, 2026, Mouser):
- TLC6C5712QPWPRQ1 — 0 in stock; 26-week lead time; in-transit total down to 62,000 pieces from 66,000 yesterday, with batches pushed later into 2027
- TPS62811QWRWYRQ1 — 0 in stock; 26-week lead time; 21,000 pieces expected July 26, 2027
- TPS1HB16AQPWPRQ1 — 0 in stock; 26-week lead time; 39,500 pieces in transit, all due in 2027
One honest note on today’s reading: the TI figures above are our own measured checks. The ST, NXP and Microchip figures are reported by TrendForce and the companies’ earnings calls, not measured by us — and the reported AMD increase for December 27 remains unconfirmed by the factory, with no new evidence today.
What this means for buyers
- Price rises land on January 1. ST’s fourth increase takes effect on the first day of 2027, and foundry and packaging rises are expected the same month. If your BOM carries ST, NXP, TI or Microchip analog parts, confirm lots before the new year rather than after the new price lists arrive.
- 16 weeks is now normal for most NXP lines. Four in five NXP products sit past the 16-week mark, against one in four a year ago. A 16-week lead time ordered today lands in March 2027 — plan first-quarter builds now, not in January.
- TI’s rise is already in distributor pricing. The 10–15% increase shows up in the Deutsche Bank distributor survey, and the three TI power parts we track daily are all at zero stock with 26-week lead times and shrinking in-transit totals. Check both channels before you conclude a part is unavailable — one channel’s zero has before turned out to be stock at another.
- Mature-node capacity is the squeeze point. 8-inch capacity is shrinking while AI and industrial demand absorbs wafer starts and back-end slots. Long-term supply agreements are how some buyers are securing analog supply; spot availability for mature-node parts will stay tight.
- Our FPGA lines are unchanged today. The ten core Xilinx parts we track daily showed no movement — eight still at zero stock with 40–52-week lead times, and the Artix-7 XC7A35T-2FTG256I still low at about 62 pieces across the two channels we check.
If any analog, power or FPGA line on your BOM needs a confirmed lot, send us your shortage list. We check real availability lot by lot. Request a Quote: https://iccpower.com/request-a-quote/
We reply to every inquiry within 24 hours.